Power distribution tests

Scheduled for Mon, Nov 24, 2025 09:00

Schedule/description of work

We want to test several components in our power distribution chain. To do this, we need to bring up the site load. During this test we will install a loadbank to bring up the total site load to its potential maximum. This will be done in phases. No impact is expected. A more accurate date and time will be given when possible.

Scheduled start time
Monday, Nov 24, 2025 09:00
Expected end time
Friday, Nov 28, 2025 16:00
Status
Scheduled