Upgrade of UPS system

Scheduled for Mon, Oct 13, 2025 08:00

Schedule/description of work

To accomodate for extra IT power availability in the upcoming years, we are performing an upgrade of our UPS system. This will be performed in week 42, starting October 13, and will take approximately 5 days. During the maintenance each UPS set will be switched off and on. No impact is expected as our other UPS sets will take over the load during all times.

Scheduled start time
Monday, Oct 13, 2025 08:00
Expected end time
Friday, Oct 17, 2025 17:00
Status