  • Power

Upgrade of UPS system

Scheduled for Mon, Oct 13, 2025 08:00

Schedule/description of work

To accomodate for extra IT power availability in the upcoming years, we are performing an upgrade of our UPS system. This will be performed in week 42, starting October 13, and will take approximately 5 days. To perform the work we need to switch off each UPS one by one. After the battgery upgrsde is done, we need to shut off and bypass the complete system to activate the new setup. During that time, we will run on our generators. This will take approximately 15 minutes. This will be done on Wednesday between 10:00 and 14:00 CEST.

Scheduled start time
Monday, Oct 13, 2025 08:00
Expected end time
Friday, Oct 17, 2025 17:00
Status
Completed